Damen Shipyards Yichang put into operation the lead for this shipyard tanker DT8000 SD built according to the RST27 project

On January 24, 2018 the Damen Shipyards Yichang (China) put into operation its lead DAMEN Tanker 8000 Shallow Draft (DT8000 SD) "Maaike" built according to the RST27 project (building No. 559005).
 
Keel of the first vessel was laid down on 24.05.16. She was launched on 20.09.17. The second tanker is also at the high grade of readiness; her keel was laid down on 20.06.16.
 
Source of photographs is Information & Analytical Agency PortNews.
 
Responding to direct market demand, the tanker is built for future use (in store), and is ready for delivery to potential customers.
 
The international shipbuilding group DAMEN Shipyards Group (head office in Gorinchem, the Netherlands) unites 40 ship-building and ship-repairing shipyards. The total staff of the company around the world is 9 thousand people. As of today, the company built more than 6 thousand vessels around the world; annually about 160 new vessels are put into operation. DAMEN specializes in design and construction of tugboats, boats, patrol ones, high-speed and cargo vessels, dredges, ships for servicing offshore platforms, oil spill response vessels, frigates and mega-yachts.
 
Project RST27 was designed by Marine Engineering Bureau.
 
Britain Royal Institution of Naval Architects included RST27 in the list of the best vessels of the year (Significant Ships of 2012 and Significant Ships of 2013).
 
Series of tankers with an increased block coefficient prj. RST27 is the biggest in new history of national shipbuilding, from 2012 40 vessels has been built and taken in to operation.
 
RST27 vessels have the record block coefficient 0.93, but the head vessel showed speed of 11.7 kn during trials at running line with main engines power of 2100 kW (87.5% of full output) and fore/aft draughts 3.2/3.3 m.
 
New project tanker has increased river function comparing with other MEB projects. River deadweight of RST27 vessels is increased for 732 t comparing to Armadas, while:
 
• increased hull's strength (vessel is of R2 sailing region, or II region due to old RS classification);
• practically keeping the same fuel consumption;
• keeping increase capacity of cargo tanks.
 
Russian Maritime Registry of Shipping class notation is - KM Ice1 R2 AUT1-ICS OMBO VCS ECO-S Oil tanker (ESP).
 
As other river-sea going MEB tankers, RST27 vessels use full-circle rudder propellers as single movement and maneuver unit. They have increased trunk and use submersible cargo pumps. They have no longitudinal bulkhead in CL and no framing in cargo tanks.
 
RST27 vessels satisfy dimensions of the Volga-Don Canal and Volga-Baltic Way. Overall RST27 vessel length is of 140.85 m, breadth is of 16.6 m, depth is of 6.0 m. They belong to "Volgo-Don Max" class.
 
Special requirements of the Russian and world petroleum companies, additional ecological RS limitations of "ECO PROJECT" (ECO-S) class were taken into consideration during designing.
 
RST27 vessels are assigned for transportation of crude oil and oil products, without flash point restrictions.
 
Simultaneous transportation of two types of cargo is ensured.
 
Total capacity of six cargo tanks and two slop ones is of 8100 cub. m, deadweight is about 7022 tons with sea draught of 4.20 m. Deadweight is about 5420 tons with river draught of 3.60 m. Cruising speed is of 11.0 knots.
 
Cargo system provides simultaneously transportation of 2 cargoes. Cargo pumps capacity is 6 x 200 cub. m/hour. Two auxiliary steam boilers (capacity 2.5 t/hour each) are installed onboard.
 
Two medium-speed diesels (main engine) of 1200 kW each use heavy fuel oil with viscosity IFO380. There is 230 kW bow thruster.
 
Electrical plant consists of three 292 kW diesel-generators and emergency-staying 136 kW diesel-generator.
 
Crew consists of 12 persons (14 places + pilot).
 
Autonomy is of 20/12 days (sea/river).
 
Keel of the RST27 lead vessel (at Krasnoe Sormovo Shipyard) "VF Tanker-1" (building No. 02001) was laid down on 30.08.11. She was launched on 17.02.12 and put into operation on 05.05.12.
Keel of the second vessel "VF Tanker-2" (building No. 02002) was laid down on 15.11.11. She was launched on 14.04.12 and put into operation on 23.05.12.
Keel of the third vessel "VF Tanker-3" (building No. 02003) was laid down on 03.10.11. She was launched on 17.03.12 and put into operation on 17.05.12.
Keel of the fourth vessel "VF Tanker-4" (building No. 02004) was laid down on 20.12.11. She was launched on 18.05.12 and put into operation on 09.06.12.
Keel of the fifth vessel "VF Tanker-5" (building No. 02005) was laid down on 15.12.11. She was launched on 15.06.12 and put into operation on 10.07.12.
Keel of the sixth vessel "VF Tanker-6" (building No. 02006) was laid down on 28.02.12. She was launched on 12.07.12 and put into operation on 20.08.12
Keel of the seventh vessel "VF Tanker-7" (building No. 02007) was laid down on 30.03.12 She was launched on 16.08.12 and put into operation on 17.09.12.
Keel of the eighth vessel "VF Tanker-8" (building No. 02008) was laid down on 30.04.12. She was launched on 28.09.12 and put into operation on 12.10.12.
Keel of the ninth vessel "VF Tanker-9" (building No. 02009) was laid down on 08.06.12. She was launched on 19.10.12 and put into operation on 29.10.12.
Keel of the tenth vessel "Constructor Zhivotovskiy" (building No. 02010) was laid down on 31.07.12. She was launched on 23.04.13 and put into operation on 15.03.13.
Keel of the eleventh vessel "Valentin Gruzdev" (building No. 02011) was laid down on 27.09.12. She was launched on 17.05.13 and put into operation on 28.03.14.
Keel of the twelfth vessel "Dmitry Pokrovskiy" (building No. 02012) was laid down on 31.10.12. She was launched on 28.05.13 and put into operation on 28.03.14.
Keel of the thirteenth vessel "Lady Leila" (building No. 02013) was laid down on 02.14.13. She was launched on 08.05.14 and put into operation on 24.06.14.
Keel of the fourteenth vessel "Lady Sevda" (building No. 02014) was laid down on 15.14.13. She was launched on 12.09.14 and put into operation on 30.09.14.
Keel of the fifteenth vessel "Synergy 1" (building No. 02015) was laid down on 09.06.14. She was launched on 17.04.15 and put into operation on 02.06.15.
Keel of the sixteenth vessel "Synergy 2" (building No. 02016) was laid down on 23.06.14. She was launched on 08.05.15 and put into operation on 13.06.15.
Keel of the seventeenth vessel "Victoria" (building No. 02017) was laid down on 25.12.14. She was launched on 10.09.15 and put into operation on 30.09.15.
Keel of the eighteenth vessel "Balt-Flot 11" (building No. 02018) was laid down on 25.09.15. She was launched on 25.03.16 and put into operation on 11.05.16.
Keel of the nineteenth vessel "Balt-Flot 12" (building No. 02019) was laid down on 20.11.15. She was launched on 11.05.16 and put into operation on 07.07.16.
Keel of the twentieth vessel "Ganja" (building No. 02020) was laid down on 23.12.15. She was launched on 19.08.16. and put into operation on 19.10.16.
Keel of the twenty-first vessel "Professor Aziz Aliyev" (building No. 02021) was laid down on 15.04.16. She was launched on 17.02.17. and put into operation on 20.06.17.
Keel of the twenty-second vessel "Volgotrans-2701" (building No. 02023) was laid down on 31.05.16. She was launched on 24.03.17. and put into operation on 10.07.17.
Keel of the twenty-third vessel "Volgotrans-2702" (building No. 02024) was laid down on 28.07.16. She was launched on 05.05.17. and put into operation on 24.07.17.
 
Keel of RST27 lead vessel (at Oka Shipyard) "VF Tanker-11" (building No. 02701) was laid down on 20.10.11. She was launched on 27.04.12 and put into operation on 17.07.12.
Keel of the second vessel "VF Tanker-12" (building No. 02702) was laid down on 27.10.11. She was launched on 01.06.12 and put into operation on 17.08.12.
Keel of the third vessel "VF Tanker-13" (building No. 02703) was laid down on 27.12.11. She was launched on 28.07.12 and put into operation on 25.09.12.
Keel of the fourth vessel "VF Tanker-14" (building No. 02704) was laid down on 20.01.12. She was launched on 23.08.12 and put into operation on 02.11.12.
Keel of the fifth vessel "VF Tanker-15" (building No. 02705) was laid down on 20.03.12. She was launched on 04.10.12 and put into operation on 04.12.12.
Keel of the sixth vessel "VF Tanker-16" (building No. 02706) was laid down on 23.05.12. She was launched on 22.11.12 and put into operation on 29.04.13.
Keel of the seventh vessel "VF Tanker-17" (building No. 02707) was laid down on 20.06.12. She was launched on 08.02.13 and put into operation on 29.04.13.
Keel of the eighth vessel "VF Tanker-18" (building No. 02708) was laid down on 03.09.12. She was launched on 26.03.13 and put into operation on 31.05.13.
Keel of the ninth vessel "VF Tanker-19" (building No. 02709) was laid down on 18.10.12. She was launched on 25.04.13 and put into operation on 28.06.13.
Keel of the tenth vessel "VF Tanker-20" (building No. 02710) was laid down on 30.11.12. She was launched on 28.05.13 and put into operation on 29.07.13.
Keel of the eleventh vessel "VF Tanker-21" (building No. 02711) was laid down on 11.01.13. She was launched on 10.07.13 and put into operation on 02.09.13.
Keel of the twelfth vessel "VF Tanker-22" (building No. 02712) was laid down on 11.03.13. She was launched on 15.08.13 and put into operation on 07.10.13.
Keel of the thirteenth vessel "Balt-Flot 14" (building No. 02013) was laid down on 07.10.15. She was launched on 08.06.16.
Keel of the fourteenth vessel "Balt-Flot 15" (building No. 02714) was laid down on 14.12.15.
 
Keel of RST27 lead vessel (at Damen Shipyards Yichang) DT8000 SD "Maaike" (building No. 559005) was laid down on 24.05.16. She was launched on 20.09.17 and put into operation on 24.01.18.
Keel of the second vessel (building No. 559006) was laid down on 20.06.16.