16.07.21 18:07
Krasnoe Sormovo accepted for operation its twenty seventh multipurpose RSD59 dry cargo vessel "Alfa Gelios" of 8144 t deadweight

On 14.07.2021 Krasnoe Sormovo Shipyard (director Mikhail Pershin) accepted for operation its twenty seventh multipurpose RSD59 dry cargo vessel "Alfa Gelios" of 8144 t deadweight (building No. 06027) and the seventh vessel in a series of nine RSD59 vessels for the "Alfa" company.
 
The head vessel of the series m\v "Pola Makaria" was included in the list of Significant Ships of 2018 of the Royal Institution of Naval Architects (RINA).
 
The RSD59 prj. was designed by Marine Engineering Bureau.
 
Krasnoe Sormovo Shipyard has already built 27 multipurpose RSD59 dry cargo vessels, 2 more launched. The competition for 11 more RSD59 vessels has been completed.
 
For information: Nevsky Shipyard has put into operation three RSD59 vessels, 2 more ones are under construction.
 
Oka Shipyard has signed contract for more 18 RSD59 vessels. Eleven are accepted for operation.
 
By other words, the total order for RSD59 vessels is 63 vessels for the moment (41 ones has been constructed, 11 are in work, and 11 are in option).
 
RSD59 vessels refer to the "Volga-Don Max" type due to MEB internal classification. They have maximum possible dimensions for the Volga-Don Canal.
 
Vessels of the series can be operated for transportations of general, bulk, timber, grain and large-sized cargoes, dangerous goods of 1.4S, 2, 3, 4, 5, 6.1, 8, 9 classes of IMDG Code and cargoes of category B of IMSBC Code. Sailing regions are Mediterranean, Caspian, Black, Baltic, White, North Seas, including voyages around Europe and to Irish Sea in winter. The new dry-cargo project RSD59, which is constructed in "super-full" ship lines with two dry cargo holds, one of which has a record length for Volgo-Don Max vessels, is the successor of the three-hold RSD49 series.
 
Advantages of the RSD59 project in comparison with the best of the previously constructed dry cargo vessels of the Volga-Don Max class of the RSD49 project (by the example of m/v "Pola Fiva" with increased marine function):
 
• the existence of a long L = 77.35 m hold (RSD49 vessel has L = 52 m cargo hold) that allows transportation of oversized and heavy cargo; this is relevant for the market of the Caspian region countries;
• the hold's height is increased up to 9000 mm, that is 620 mm bigger than for RSD49 project. Such height allows to load 9'6'' containers ("high cube containers"), 3 ones in single stack;
• deadweight at draught of 3.60 m is 5320 t (RSD49 has 4507 t), increase is 813 t;
• deadweight at a draught of 4.20 m 6944 tons (RSD49 project has 6021 t), increased by 923 t;
• deadweight at the maximum draught of 4.706 m is 8144 t (RSD49 has 7143 t at maximum draught of 4.70 m), increase is 1000 t;
• removable type hatch covers are installed. Opening and closing of each section is operated with the help of a special frame crane, which is located in the area of the front bulkhead of the residential superstructure;
• movement and controllability are provided by two rudder propeller units (better maneuverability in the narrow waters, more cargo space due to the reduction of size of engine room).
 
The project is designed for a class notation KM Ice2(hull; power) R2 AUT1-ICS BWM(T) CONT (deck, cargo holds Nos.1,2) DG (bulk, pack) of Russian Maritime Register of Shipping and meets all the requirements of international conventions acted at the moment of the vessel's keel laying.
 
In this case, RSD59 vessels' deadweight is the largest for dry cargo vessels satisfying the dimensions of the Volga-Don Shipping Channel.
 
For characteristic for the VDSC draught of 3.60 m, river deadweight is 5320 t; the largest marine deadweight for draught 4.706 m is 8144 t.
 
The maximum length is 141.0 m, the overall width is 16.98 m, depth is 6.00 m.
 
The capacity of cargo holds is 11400 cubic m.
 
Both cargo holds are box-shaped, smooth-walled, and convenient at cargo operations and placing the goods without stowage. Their dimensions are 77.35 x 12.25 x 9.0 m and 27.03 x 12.25 x 9.0 m.
 
The operating speed is 10.5 knots.
 
Two medium-speed diesels (main engine) of 1200 kW each use heavy fuel oil with viscosity of IFO380 Heavy fuel stores are placed in deep-tanks in area of the ER fore bulkhead, separated from outside water by double bottom and double sides.
 
Sea sailing autonomy is 20 day.
 
Crew consists of 11 people, total places onboard are 14. Sanitary and pilot cabins are provided.
 
Designed vessel hull's life term is 24 years. The double bottom is designed for distributed load with intensity of 12 tons per square meter, and also allows to use 16 t bucket grab.
 
Keel of the RSD59 lead vessel (at Krasnoe Sormovo Shipyard) "Pola Makaria" (building No. 06001) was laid down on 05.09.17. She was launched on 20.04.18 and accepted for operation on 24.05.2018.
Keel of the second vessel "Pola Filofea" (building No. 06002) was laid down on 19.09.17. She was launched on 08.06.2018 and accepted for operation on 05.07.2018.
Keel of the third vessel "Pola Sofia" (building No. 06003) was laid down on 25.09.17. She was launched on 12.07.2018 and accepted for operation on 08.08.2018.
Keel of the fourth vessel "Pola Feodosia" (building No. 06004) was laid down on 20.12.17. She was launched on 17.08.18 and accepted for operation on 14.09.2018.
Keel of the fifth vessel "Pola Fiva" (building No. 06005) was laid down on 25.12.17. She was launched on 21.09.18 and accepted for operation on 15.10.2018.
Keel of the sixth vessel "Idel 1" (building No. 06006) was laid down on 25.09.18. She was launched on 21.02.19 and accepted for operation on 16.05.2019.
Keel of the seventh vessel "Idel 2" (building No. 06007) was laid down on 27.11.18. She was launched on 05.04.19 and accepted for operation on 23.05.2019.
Keel of the eighth vessel "Idel 3" (building No. 06008) was laid down on 14.12.18. She was launched on 14.05.19 and accepted for operation on 28.06.2019.
Keel of the ninth vessel "Andrey Zuev" (building No. 06009) was laid down on 28.02.19. She was launched on 21.06.19 and accepted for operation on 16.07.2019.
Keel of the tenth vessel "Pola Harita" (building No. 06010) was laid down on 18.04.19. She was launched on 02.08.19 and accepted for operation on 06.09.2019.
Keel of the eleventh vessel "Pola Pelagia" (building No. 06011) was laid down on 21.05.19. She was launched on 20.09.2019 and accepted for operation on 11.10.2019.
Keel of the twelfth vessel "Aleksandr Sokolov" (building No. 06012) was laid down on 28.06.19. She was launched on 25.10.2019 and accepted for operation on 12.11.2019.
Keel of the thirteenth vessel "Pola Anastasia" (building No. 06013) was laid down on 20.08.19. She was launched on 12.12.2019 and accepted for operation on 02.05.2020.
Keel of the fourteenth vessel "Pola Maria" (building No. 06014) was laid down on 30.09.19. She was launched on 30.01.2020 and accepted for operation on 29.04.2020.
Keel of the fifteenth vessel "Pola Yaroslava" (building No. 06015) was laid down on 01.11.19. She was launched on 05.03.2020 and accepted for operation on 03.05.2020.
Keel of the sixteenth vessel "Pola Varvara" (building No. 06016) was laid down on 02.12.19. She was launched on 17.04.2020 and accepted for operation on 05.06.2020.
Keel of the seventeenth vessel "Pola Agata" (building No. 06017) was laid down on 22.01.20. She was launched on 27.05.2020 and accepted for operation on 23.07.2020.
Keel of the eighteenth vessel "Pola Aleksia" (building No. 06018) was laid down on 21.02.20. She was launched on 26.06.2020 and accepted for operation on 20.08.2020.
Keel of the nineteenth vessel "Pola Marina" (building No. 06019) was laid down on 27.03.20. She was launched on 07.08.2020 and accepted for operation on 10.09.2020.
Keel of the twentieth vessel "Pola Miropia" (building No. 06020) was laid down on 06.05.20. She was launched on 04.09.2020 and accepted for operation on 30.09.2020.
Keel of the twenty first vessel "Alfa Atlant" (building No. 06021) was laid down on 08.06.20. She was launched on 30.09.2020 and accepted for operation on 17.11.2020.
Keel of the twenty second vessel "Alfa Merkuriy" (building No. 06022) was laid down on 06.07.20. She was launched on 23.10.2020 and accepted for operation on 03.12.2020.
Keel of the twenty third vessel "Vladimir Latyshev" (building No. 06023) was laid down on 07.08.20. She was launched on 11.12.2020 and accepted for operation on 28.04.2021.
Keel of the twenty fourth vessel "Viktor Andryukhin" (building No. 06024) was laid down on 21.09.20. She was launched on 20.01.2021 and accepted for operation on 10.06.2021.
Keel of the twenty fifth vessel "Leonid Pestrikov" (building No. 06025) was laid down on 06.10.20. She was launched on 12.02.2021 and accepted for operation on 07.07.2021.
Keel of the twenty sixth vessel "Nikolay Leonov" (building No. 06026) was laid down on 20.10.20. She was launched on 14.04.2021 and accepted for operation on 14.07.2021.
Keel of the twenty seventh vessel "Alfa Gelios" (building No. 06027) was laid down on 03.11.20. She was launched on 29.04.2021 and accepted for operation on 14.07.2021.
Keel of the twenty eighth vessel "Alfa Germes" (building No. 06028) was laid down on 20.11.20. She was launched on 03.06.2021.
Keel of the twenty ninth vessel "Alfa Aquilon" (building No. 06029) was laid down on 10.12.20. She was launched on 09.07.2021.