10.04.15 10:58
RST27 vessel "VF Tanker-18" owned by "V.F.Tanker" Shipping Company opened river navigation in Saratov


Due to information from "V.F.Tanker" Shipping Company, RST27 vessel "VF Tanker-18" of "Volgo-Don Max" type have departed from Saratov with diesel oil cargo onboard.
 
Oka Shipyard (Vladimir Kulikov is a director) is a builder of the vessel. Keel of the vessel was laid down on 03.09.2012. She was launched on 26.03.2013 and put into operation on 31.05.2013.
 
"V.F.Tanker" Shipping Company have received 22 RST27 "super fat" tankers from Oka Shipyard and Krasnoe Sormovo Shipyard during 2012-2013.
 
"Company is included in the VBTH Holding, which is shipping department of international transport group Universal Cargo Logistics Holding (UCLH). UCLH is a majority stockholder of VBTH holding; it consolidates a group of Russian rail-way, stevedoring and logistic companies. VBTH also includes Volga and North-West Shipping Companies and some shipbuilding and cruise enterprises.
 
Project RST27 was designed by Marine Engineering Bureau.
 
Contract deadweight of 6980/5378 t was increased for "VF tanker-11" by 50 t and actually is of 7030/5428 t. Speed was of 11.7 knots during running test.
 
New project tanker has increased river function comparing with other MEB projects. River deadweight of RST27 prj. vessels is increased for 716 t comparing to Armadas, while:
 
• increased hull's strength (vessel is of R2 sailing region, or II region due to old RS classification);
• practically keeping the same fuel consumption;
• keeping increase capacity of cargo tanks.
 
"Super-fat" vessel's shape is a result of scientific research carried out by Marine Engineering Bureau in 2010 and were defined with help of calculating hydromechanics methods (CFD modeling).
 
As other river-sea MEB tankers, RST27 vessels use full-circle rudder propellers as single movement and manoeuvre unit. They have increased trunk and use submersible cargo pumps. They have no longitudinal bulkhead in CL and no framing in cargo tanks.
 
Russian Maritime Registry of Shipping class notation is KM Ice1 R2 AUT1-ICS OMBO VCS ECO-S Oil tanker/ chemical tanker Type 2 (ESP).
 
RST27 vessels satisfy dimensions of the Volga-Don Canal and Volga-Baltic Way. Overall RST27 vessel's length is 140.85 m, breadth is 16.6 m, depth is 6.0 m. They belong to "Volgo-Don Max" type.
 
Special requirements of the Russian and world petroleum companies, additional ecological RS limitations of "ECO PROJECT" (ECO-S) class were taken into consideration during designing.
 
RST27 vessels (tanker/product carrier/chemical carrier type) are assigned for transportation of crude oil and oil products without flash point restrictions and also vegetable oils.
 
Total capacity of six cargo tanks and two slop ones is of 8100 cub. m, deadweight is about 7030 tons at sea draught 4.20 m. Deadweight is 5428 tons at river draught 3.60 m. Operational speed is 10.5 knots.
 
Cargo system provides simultaneously transportation of 2 cargoes. Cargo pumps capacity is 6 x 200 cub. m/hour. Two auxiliary steam boilers (capacity 2.5 t/hour each) are installed onboard.
 
Two medium-speed diesels (main engine) of 1200 kW each use heavy fuel oil with viscosity IFO380. There is 230 kW bow thruster. Electrical plant consists of three 292 kW diesel-generators and emergency-staying 136 kW diesel-generator.
 
Crew consists of 12 persons (14 places + pilot).
 
Autonomy is of 20/12 days (sea/river).
 
Keel of RST27 lead vessel (at Oka Shipyard) "VF Tanker-11" (building No. is of 02701) was laid down on 20.10.11. She was launched on 27.04.12 and put into operation on 17.07.12.
Keel of RST27 second vessel "VF Tanker-12" (building No. is of 02702) was laid down on 27.10.11. She was launched on 01.06.12 and put into operation on 17.08.12.
Keel of RST27 third vessel "VF Tanker-13" (building No. is of 02703) was laid down on 27.12.11. She was launched on 28.07.12 and put into operation on 25.09.12.
Keel of RST27 fourth vessel "VF Tanker-14" (building No. is of 02704) was laid down on 20.01.12. She was launched on 23.08.12 and put into operation on 02.11.12.
Keel of RST27 prj. fifth vessel "VF Tanker-15" (building No. is of 02705) was laid down on 20.03.12. She was launched on 04.10.12 and put into operation on 04.12.12.
Keel of RST27 prj. sixth vessel "VF Tanker-16" (building No. is of 02706) was laid down on 23.05.12. She was launched on 22.11.12 and put into operation on 29.04.13.
Keel of RST27 seventh vessel "VF Tanker-17" (building No. is of 02707) was laid down on 20.06.12. She was launched on 08.02.13 and put into operation on 29.04.13.
Keel of RST27 eighth vessel "VF Tanker-18" (building No. is of 02708) was laid down on 03.09.12. She was launched on 26.03.13 and put into operation on 31.05.13.
Keel of RST27 ninth vessel "VF Tanker-19" (building No. is of 02709) was laid down on 18.10.12. She was launched on 25.04.13 and put into operation on 28.06.13.
Keel of RST27 tenth vessel "VF Tanker-20" (building No. is of 02710) was laid down on 30.11.12. She was launched on 28.05.13 and put into operation on 29.07.13.
Keel of RST27 eleventh vessel "VF Tanker-21" (building No. is of 02711) was laid down on 11.01.13. She was launched on 10.07.13 and put into operation on 02.09.13.
Keel of RST27 twelfth vessel "VF Tanker-22" (building No. is of 02712) was laid down on 11.03.13. She was launched on 15.08.13 and put into operation on 07.10.13.
 
Keel of RST27 lead vessel (at the Kherson Shipyard) "SVL-Liberty" (building No. is of 8001) on 23.11.2011. She was launched on 19.10.12 and put into operation 22.03.2013.
Keel of RST27 second vessel "SVL Loyalty" was laid down on 22.12.2011 (building No. is of 8002). She was launched on 17.05.2013 and put into operation on 12.07.2013.
Keel of RST27 third vessel "SVL Unity" was laid down on 22.03.2012 (building No. is of 8003). She was launched on 21.06.2013 and put into operation on 30.08.2013.
 
Keel of the lead vessel (at Krasnoe Sormovo Shipyard) "VF Tanker-1" (building No. is of 02001) was laid down on 30.08.11. She was launched on 17.02.12 and put into operation on 05.05.12.
Keel of the second vessel "VF Tanker-2" (building No. is of 02002) was laid down on 15.11.11. She was launched on 14.04.12 and put into operation on 23.05.12.
Keel of the third vessel "VF Tanker-3" (building No. is of 02003) was laid down on 03.10.11. She was launched on 17.03.12 and put into operation on 17.05.12.
Keel of the fourth vessel "VF Tanker-4" (building No. is of 02004) was laid down on 20.12.11. She was launched on 18.05.12 and put into operation on 09.06.12.
Keel of the fifth vessel "VF Tanker-5" (building No. is of 02005) was laid down on 15.12.11. She was launched on 15.06.12 and put into operation on 10.07.12.
Keel of the sixth vessel "VF Tanker-6" (building No. is of 02006) was laid down on 28.02.12. She was launched on 12.07.12 and put into operation on 20.08.12.
Keel of the seventh vessel "VF Tanker-7" (building No. is of 02007) was laid down on 30.03.12 She was launched on 16.08.12 and put into operation on 17.09.12.
Keel of the eighth vessel "VF Tanker-8" (building No. is of 02008) was laid down on 30.04.12. She was launched on 28.09.12 and put into operation on 12.10.12.
Keel of the ninth vessel "VF Tanker-9" (building No. is of 02009) was laid down on 08.06.12. She was launched on 19.10.12 and put into operation on 29.10.12.
Keel of the tenth vessel "Constructor Zhivotovskiy" (building No. is of 02010) was laid down on 31.07.12. She was launched on 23.04.13 and put into operation on 15.03.13.
Keel of the eleventh vessel "Valentin Gruzdev" (building No. is of 02011) was laid down on 27.09.12. She was launched on 17.05.13 and put into operation on 28.03.14.
Keel of the twelfth vessel "Dmitry Pokrovskiy" (building No. is of 02012) was laid down on 31.10.12. She was launched on 28.05.13 and put into operation on 28.03.14.
Keel of the thirteenth vessel "Lady Leila" (building No. is of 02013) was laid down on 02.14.13. She was launched on 08.05.14 and put into operation on 24.06.14.
Keel of the fourteenth vessel "Lady Sevda" (building No. is of 02014) was laid down on 15.14.13. She was launched on 12.09.14 and put into operation on 30.09.14.